Pouring the Floors
After the troughs were all cured, and the radiantly-heated floors of the mikvah room and prep rooms were cured, we poured the …
After the troughs were all cured, and the radiantly-heated floors of the mikvah room and prep rooms were cured, we poured the …
We are pleased to announce that our mikvah will be named Mikvah Mayanei Tova in memory of Mrs. Toby Sontag, A”H of …
Once the otzar had sat for two weeks with water, to test it for leaks and to activate the Xypex (the waterproofing …
Now that the in-floor plumbing is done, we’re ready to back fill with sand, construct the forms for the floor, and lay …
In the name of efficiency, we wanted to pour the concrete for the floors at the same time as pouring the remainder …
After the stairs and the otzar were poured, they set for a week to cure. The floor of the mikvah and the …